ASTA: Difference between revisions

From Rsewiki
 
(142 intermediate revisions by 2 users not shown)
Line 1: Line 1:




[[File:die_asta.png | 200px]] (jyllands-posten.dk)


=Autonomous Systems Test Arena=


Our new facility for cooperating autonomous systems - in air, on the ground, on water and below water.
=Autonomous Systems Test Arena (building 330D)=


Our new facility for cooperating autonomous systems - in air, on the ground, on water and below the water surface.


[[File:artist-impression.png | 600px]]
[[File:asta_as_of_06_apr_2020_1.jpg | 450px]]
[[File:asta_as_of_8_nov_2019.jpg | 500px]]


Rambøl - expected view of building from the south and current view (8 Nov 2019).
===Status===


=== Sub-pages===
28 June 2021:
Fully operational (:D)


* [[Fence blocks]] - former Autonomous Eco-car fence
=== Instructions ===


* [[Drone net]] - drone net mounting
* [[ASTA access]] - instruction for access


===Sketch of building 330D ===
* [[ASTA pool]] - instructions for pool use and maintenance.


[[File:ASTA-onshape-drawing_02.png | 500px]]...
* [[ASTA motion capture]] - instructions for use
[[File:ASTA-overview-21-oct-2019.png | 500px]]


Overall sketch of the facility, an air dome, about 23 x 40m with a roof height of 14m.
* [[ASTA booking]] - instructions for booking.
The dome is divided into 3 sections with drone (removable) net. In one end is a pool 3.5 x 6.5 x 3m deep and in the same area a camera localization system for accurate ground truth localization.


=== Current state ===
=== ASTA insides ===


====October 2019 ====
* [http://aut.elektro.dtu.dk/rse/ASTA/asta_view.html View to ASTA] (must be on local net (10.59.8/9.x) to work)


[[File:fundament_23oct2019.png | 400px]]
* [[Building history]] - pictures from process


as of 23 October 2019. Edge foundation started.
===Maintainer===


====November 2019 ====
This page is (mainly) maintained by Christian Andersen (jcan@dtu.dk)
 
[[File:asta_as_of_4_nov_2019.png | 400px]]
 
as of 4 November 2019. The first level of concrete in place.
 
[[File:asta_as_of_8_nov_2019_before_pool.jpg | 400px]]
 
As of 8 nov 2019. Concrete form for foundation cast in place. This is the corner, where the pool is to be placed.
 
[[File:asta_as_of_11_nov_2019.jpg | 400px]]
 
As of 11 nov 2019. The final height of foundation being marked and in-door floor levelling in the background (before asphalt) - except for pool area (upper left).
 
[[File:asta_as_of_14_nov_2019.jpg | 400px]]
[[File:asta_as_of_14_nov_2019_entrance.jpg | 400px]]
 
As of 14 nov 2019. Most of the foundation is now cast and the form is being removed. The casting of the entrance part of the foundation is being prepared.
 
[[File:asta_as_of_18_nov_2019.jpg | 400px]]
 
As of 18 Nov 2019. The foundation looks good and excavating for the pool has started. The plan is to cast the entrance on Wednesday and the bottom of the pool-hole on Friday, ready for the pool team on Monday 27 Nov.
 
[[File:asta_as_of_20_nov_2019.jpg | 400px]]
[[File:asta_as_of_20_nov_2019_entrance_cast.jpg | 400px]]
 
As of 20 Nov 2019. Pool pit started and final part of foundation (entrance) cast.
 
====December 2019 ====
 
Then the pool and outside drainage is next.
 
After that the indoor asphalt and foundation for entrance, gate and emergency exits.
 
====January 2020====
 
Dome delivery and mounting in January 2020.
 
====February 2020====
 
Dome inflation and in-door preparation in February 2020.
 
This page is maintained by jca@elektro.dtu.dk

Latest revision as of 14:03, 2 March 2023



Autonomous Systems Test Arena (building 330D)

Our new facility for cooperating autonomous systems - in air, on the ground, on water and below the water surface.

Status

28 June 2021: Fully operational (:D)

Instructions

  • ASTA pool - instructions for pool use and maintenance.

ASTA insides

Maintainer

This page is (mainly) maintained by Christian Andersen (jcan@dtu.dk)