Line 35: | Line 35: | ||
[[File:asta_as_of_8_nov_2019_before_pool.jpg | 400px]] | [[File:asta_as_of_8_nov_2019_before_pool.jpg | 400px]] | ||
As of 8 nov 2019. Concrete form for foundation cast in place | As of 8 nov 2019. Concrete form for foundation cast in place. This is the corner, where the pool is to be placed. | ||
[[File:asta_as_of_11_nov_2019.jpg | 400px]] | [[File:asta_as_of_11_nov_2019.jpg | 400px]] | ||
As of 11 nov 2019. The final height of foundation being marked and in-door floor levelling (before asphalt) - except for pool area (upper left). | |||
Foundation concrete cast planned for Wednesday 13 nov. | |||
Then the pool preparation is next. | Then the pool preparation is next. |
Revision as of 10:59, 11 November 2019
Autonomous Systems Test Arena
Our new facility for cooperating autonomous systems - in air, on the ground, on water and below water.
Rambøl - expected view of building from the south and current view (8 Nov 2019).
Sketch of building 330D
Overall sketch of the facility, an air dome, about 23 x 40m with a roof height of 14m. The dome is divided into 3 sections with drone (removable) net. In one end is a pool 3.3 x 6.5 x 3m and in the same area a camera localization system for accurate ground truth localization.
Current state
as of 23 October 2019. Edge foundation started.
as of 4 November 2019. The first level of concrete in place.
As of 8 nov 2019. Concrete form for foundation cast in place. This is the corner, where the pool is to be placed.
As of 11 nov 2019. The final height of foundation being marked and in-door floor levelling (before asphalt) - except for pool area (upper left).
Foundation concrete cast planned for Wednesday 13 nov.
Then the pool preparation is next.
After that the indoor asphalt and foundation for entrance, gate and emergency exits.
Dome delivery and mounting in January 2019.
Dome inflation and in-door preparation in February 2020.