ASTA: Difference between revisions

From Rsewiki
No edit summary
Line 77: Line 77:
[[File:asta_as_of_04_dec_2019_2.jpg | 400px]]
[[File:asta_as_of_04_dec_2019_2.jpg | 400px]]


As of 4 Dec 2019. All quiet, waiting for the pool.
As of 4 Dec 2019. All quiet, waiting for the pool people.


Then the pool and outside drainage is next.
Then the pool and outside drainage is next.

Revision as of 15:07, 4 December 2019


(jyllands-posten.dk)

Autonomous Systems Test Arena

Our new facility for cooperating autonomous systems - in air, on the ground, on water and below water.


Rambøl - expected view of building from the south and current view (22 Nov 2019).

Sub-pages

Sketch of building 330D

...

Overall sketch of the facility, an air dome, about 23 x 40m with a roof height of 14m. The dome is divided into 3 sections with drone (removable) net. In one end is a pool 3.5 x 6.5 x 3m deep and in the same area a camera localization system for accurate ground truth localization.

Current state

October 2019

as of 23 October 2019. Edge foundation started.

November 2019

as of 4 Nov 2019. The first level of concrete in place.

As of 8 Nov 2019. Concrete form for foundation cast in place. This is the corner, where the pool is to be placed.

As of 11 Nov 2019. The final height of foundation being marked and in-door floor levelling in the background (before asphalt) - except for pool area (upper left).

As of 14 Nov 2019. Most of the foundation is now cast and the form is being removed. The casting of the entrance part of the foundation is being prepared.

As of 18 Nov 2019. The foundation looks good and excavating for the pool has started. The plan is to cast the entrance on Wednesday and the bottom of the pool-hole on Friday, ready for the pool team on Monday 27 Nov.

As of 20 Nov 2019. Pool pit started and final part of the foundation (entrance) cast.

As of 22 Nov 2019. Pool pit progressing and preparing for the outside drain.

As of 27 Nov 2019. The pool pit is finished and a clean base for the pool is in place. The outside drain is in progress.

December 2019

As of 4 Dec 2019. All quiet, waiting for the pool people.

Then the pool and outside drainage is next.

After that the indoor asphalt and foundation for entrance, gate and emergency exits.

January 2020

Dome delivery and mounting in January 2020.

February 2020

Dome inflation and in-door preparation in February 2020.

This page is maintained by jca@elektro.dtu.dk